The Planning Process
The Planning Process
Steeple Renewables Project would allow for the generation and export of up to 600MW of renewable energy. Given this scale, the project qualifies as a Nationally Significant Infrastructure Project (NSIP) and as such will procced through the Development Consent Order (DCO) planning process.
The DCO process provides a dedicated framework specifically designed to address the complexities associated with large, complex energy projects (as well as other project types).
Applications for DCOs are examined independently by the Planning Inspectorate. Following an examination of the project, the Planning Inspectorate will make a recommendation to the Secretary of State for the Department of Energy Security and Net Zero, who will decide on the outcome of the application.
Consultation is an important part of the DCO process as it enables everyone to comment on the proposals. The feedback received, along with further technical work and environmental studies, has informed the development of our proposals ahead of the submission of our DCO application to the Planning Inspectorate.
Pre-examination phase
Steeple Renewables Project is now in the pre-examination stage of the DCO process.
At this stage:
- The Planning Inspectorate will invite individuals, organisations, and statutory consultees to register as Interested Parties.
- Anyone who wishes to participate in the examination must submit a relevant representation to the Planning Inspectorate. You can register here. The deadline to register is 11:59pm on Thursday 28 August.
- The Examining Authority is appointed and will review all submitted representations to set out the main issues for examination.
Examination Phase
Once the pre-examination phase concludes, the project will move into the examination stage.
During this phase:
- The Examining Authority will review all submitted representations and conduct public hearings.
- Interested Parties will have opportunities to provide further input through written representations and oral evidence at hearings.
- The examination typically lasts up to six months, after which the Planning Inspectorate will submit a recommendations to the Secretary of State for Energy Security and Net Zero.
The Secretary of State will then have three months to make a final decision on whether to grant the Development Consent Order.
For more information about the planning process, please visit the Planning Inspectorate website here.
Anticipated project timeline